Up to today, the achieved SMH (safety man hours) is 546,183. 100,500 DI joints were welded, 27 sets of equipments and 154 hydro-test packages have been completed. The total progress of the Port Project is 99.03%. All the construction and hydro-test work have been finished which includes package 5, 6, Berth 37 and the two pipe racks of package 7. The hydro-test work of BNZ, HX and AT system of reconstruction project old berth 36/41/42 and 43 have been finished until now. Most of the remaining work centralizes at the joint between the new and existing pipe. There are 120 pieces of TIE-IN welding joints. TIE-IN welding joints and 4 steel platforms couldn’t be finished when the berth is busy. The unfinished mechanical work is gear pump motor solo-run and loading arm limit switch test. Recently, a lot of engineering modification and drawings update greatly increase the construction difficult.
|