Saudi Arabia SABIC 120000 tons/year butene project
admin 2010-11-26
The installation height of the Saudi SABIC 120000 tons/year butene project is high, with a maximum height of 90 meters; There is a large amount of on-site installation of equipment components, with 450 layers of trays and fasteners installed for two towers in Zone 35. The amount of work in enclosed spaces is high, and HSE management is difficult; The process pipeline has a large quantity and a short construction period. The process pipeline is 140000 inches long. Except for the pipe gallery, the installation of other areas began gradually in September 2008. Pressure testing began in October 2008 and was basically completed by the end of February.
Main physical quantities: 1424 tons of steel structure, 73 tons of dynamic equipment, 830 tons of static equipment, and 140000 inches of process pipelines. Construction period: February 2008 to June 2009.
Saudi Arabia SABIC 120000 ton Butene Plant Polypropylene Panorama ![]() Aerial View of YANSAB Petrochemical Industrial City Site of Saudi Arabia SABIC 120000 ton Butene Plant Saudi Arabia SABIC installs fire protection line for 120000 ton butene plant ![]() Saudi Arabia SABIC 120000 ton Butene Plant Butene Pipe Gallery ![]() Saudi Arabia SABIC 120000 ton Butene Plant Butene Tower and Framework Saudi Arabia SABIC 120000 ton Butene Plant Scaffold Saudi Arabia's SABIC 120000 ton butene plant is in place ![]() Saudi Arabia SABIC 120000 ton Butene Plant Tower Group ![]() Saudi Arabia SABIC 120000 ton Butene Plant Main Pipeline Corridor Area A corner of Saudi Arabia SABIC's 120000 ton butene plant |